Goals:

The purpose of the seating plan is to know the shape, composition and evolution of traffic on the road network of the Castellón Provincial Council, data that will be used for any action related to the road.

Job description:

The work developed by ABACO consists of:

  • Design of the gauging plan, categorizing the different gauging stations and scheduling the measurements to be made
  • Training to the team to carry out the installation and uninstallation of measurement equipment and the correct collection of data
  • Exploitation of the collected data
  • Delivery of the results obtained throughout the year (individual cards of each station of gauging, updated traffic map and report of results)